As part of the BREEAM Environmental Assessment, the project team is committed to publishing key facts about the design and performance of the building, including:
Basic Building Cost - £1300/m2 (of which Services Costs - £420/m2)
• External Works - £269/m2
• Gross floor area - 2338m2
• Total area of site – 1.2889 hectares
• Function areas and their size (m2) Classrooms are generally 60m2, the nursery is 65m2, there is a large reception classroom of 99m2 which can be subdivided by a folding screen. There is a hall of 155m2 with a catering kitchen of 58m2. There is also a dance/ drama/ music studio of 60m2, staff room of 52m2 and school offices, toilets, IT areas, library, group rooms and stores.
• Area of circulation 331m2
• Area of storage 120 m2
43 % area of grounds to be used by community (school field, by arrangement)
11 % area of buildings to be used by community (hall, ABC club, studio and associated circulation/ WCs)
Predicted electricity consumption - 25 kWh/m2 Predicted fossil fuel consumption - 22.5 kWh/m2
Predicted renewable energy generation - 52.5 kWh/m2
Predicted water use - 3.5 m3/person/year % predicted water use to be provided by rainwater or Greywater –not applicable
The steps taken during the construction process to reduce environmental impacts : including bat surveys, monitoring of site waste, protection of trees and reuse of crushed aggregate from the demolished old school
• External Works - £269/m2
• Gross floor area - 2338m2
• Total area of site – 1.2889 hectares
• Function areas and their size (m2) Classrooms are generally 60m2, the nursery is 65m2, there is a large reception classroom of 99m2 which can be subdivided by a folding screen. There is a hall of 155m2 with a catering kitchen of 58m2. There is also a dance/ drama/ music studio of 60m2, staff room of 52m2 and school offices, toilets, IT areas, library, group rooms and stores.
• Area of circulation 331m2
• Area of storage 120 m2
43 % area of grounds to be used by community (school field, by arrangement)
11 % area of buildings to be used by community (hall, ABC club, studio and associated circulation/ WCs)
Predicted electricity consumption - 25 kWh/m2 Predicted fossil fuel consumption - 22.5 kWh/m2
Predicted renewable energy generation - 52.5 kWh/m2
Predicted water use - 3.5 m3/person/year % predicted water use to be provided by rainwater or Greywater –not applicable
The steps taken during the construction process to reduce environmental impacts : including bat surveys, monitoring of site waste, protection of trees and reuse of crushed aggregate from the demolished old school